Contract Details

CONTRACT VALUE
$133,000.00
INDUSTRY
Construction – Apartments
COMPLETION
December 2018
CONTRACT DURATION
May 2018 to December 2018
PROJECT REFERENCE
Matt Poninghaus

Project Overview

To ensure that the floor was true for laying timber flooring, the substrate needed to be levelled. There was not sufficient budget to apply a levelling compound across the whole floor area so Surfprep inspected, surveyed and then ground the high spots to minimise the amount of filling required. This was completed to a U3 finish for the installers to work with.

Surfprep Performance

The client was pleased with the result and commented that there was excellent & reliable service from Surfprep. The preparation of the stairs followed thanks to the previous great work from Surfprep. The project was behind programme and the main contractor was pleased to have Surfprep’s no hassle attitude to get the job done.