Queens Wharf

Queens Wharf

Contract Details

CONTRACT VALUE
$30,000.00
INDUSTRY
Construction – Wharf
COMPLETION
July 2005
CONTRACT DURATION
3 Weeks

Project overview

The 2011 Queens Wharf redevelopment project managed by RCP with the main contractor Kalmar Construction, required the full range of Surfprep services. Our machinery removed concrete and asphalt that was protruding from the wharf creating an even surface to mitigate trip hazards. Our team also removed much of the redundant painted lines, texturing the surface to create slip resistance and filling holes and low spots. The overall effect was a safer pedestrian area for the downtown RWC 2011 fan zone.

Queens Wharf